Construction :
Phase 1 (22.6 km) , Phase 2 (143 km) Completed.
Phase 3 (900 km) completed.
Status of remaining work is as follows:
1. IP102A to PPN Power (162.5 Km ): Pipes received. Mainline laying work yet to be awarded.
2. IP103 to CBR Refinery (Trichy to Naganpattinam : 114 km): Mainline work completed. Work for conversion of pipeline for use as NG pipeline is in progress. Work in progress in all 6 SV locations and RT location at
Nagappattinam.
3. Tiruvallur Bangalore pipeline extension (Tattanur-SV01 Section: 6.43 Km): Hydro testing completed.
4. Thiruvallur (SV-103) to Sri city Spur line (38.16 Km): 26 Km welding and 23 Km lowering completed. | Phase 1 (22.6 km) , Phase 2 (143 km) Completed,
Phase 3 (477 km) completed. Status of remaining work is as follows:
1. IP 102 to 105 Section (Trunkline 423 km): Mainline mechanically completed.
2. IP102A to PPN Power (162.5 Km ): RoU acquisition in progress. Pipes received.
3. IP103 to CBR Refinery (Trichy to Naganpattinam : 114 km): Mainline work completed. Work for conversion of pipeline for use as NG pipeline is in progress. Work in progress in all 6 SV locations and RT location at
Nagappattinam.
4. Tiruvallur Bangalore pipeline extension (Tattanur-SV01 Section: 6.43 Km): 6.35 Km welding and 5.79 Km lowering completed.
5. Thiruvallur (SV-103) to Sri city Spur line (38.16 Km): 8.87 Km welding and 4.86 Km lowering completed. |