Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : OIL INDIA LIMITED.
Project Name : PIPELINE REHABILITATION PROJECT OF 575 KM (PHASE I).

Reported Date : 08-SEP-22

Monthly Report : 8 / 2022

  

   

Total/Pending/Completed Milestone - 12 / 6 / 6

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
4060340

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
303.3910.610314

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
10/20200/06/2022

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
200

Ministry Review Date

LatestLastPhysical Progress (%)Status
30-JUN-22100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks