Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : OIL INDIA LIMITED.
Project Name : AUGMENTATION OF PUMPING CAPACITY OF BARAUNI-BONGAIGAON SECTOR PHASE II.

Reported Date : 08-SEP-22

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 8 / 2022

Cost Overrun (%)-   0

Time Overrun (Months)-    32

Total/Pending/Completed Milestone - 22 / 16 / 6

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
571.660510

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
503.75.32511

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20198/20228/2022

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
70

Ministry Review Date

LatestLastPhysical Progress (%)Status
31-AUG-22100Completed

Monthly Status

Background Information

• Both part & Part B of the Project Commissioned on 31.12.2021 & *Project closure with additional Scope of works achieved on 10.08.2022. * All Milestones completed.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone