Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : BHARAT PETROLEUM CORPORATION LIMITED.
Project Name : LAYING OF HEAT TRACED PIPE LINE WITH ASSOCIATED FACILITIES AT MUMBAI REFINERY.

Reported Date : 14-JAN-19

Monthly Report : 11 / 2018

  

   

Total/Pending/Completed Milestone - 18 / 18 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
193.40193.4

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
41.663.172.02106.79

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
1/20190/011/2018

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
700

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Project was completed on 26th November 2018.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks