Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : BHARAT PETROLEUM CORPORATION LIMITED.
Project Name : MOTOR SPIRIT BLOCK PROJECT (MSBP) TO PRODUCE BSVI MS AT KOCHI REFINERY.

Reported Date : 09-JUL-21

Monthly Report : 6 / 2021

  

   

Total/Pending/Completed Milestone - 20 / 20 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
331303288.96

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2206.95764.415.642977

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
2/20203/20216/2021

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
3130

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

With Penex unit commissioning on 18.06.2021, all three units of MSBP commissioned..

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks