Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : GAS AUTHORITY OF INDIA LIMITED.
Project Name : LAYING OF VIJAIPUR-AURAIYA PIPELINE SECTION OF VIJAIPUR-AURAIYA-PHULPUR PIPELINE PROJECT.

Reported Date : 07-APR-22

Monthly Report : 3 / 2022

  

   

Total/Pending/Completed Milestone - 24 / 0 / 24

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2881.402000

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1612.848.226.91687.9

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20200/03/2022

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
0110

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Pipeline Commissioned

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks