Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : GAS AUTHORITY OF INDIA LIMITED.
Project Name : LAYING OF VIJAIPUR-AURAIYA PIPELINE SECTION OF VIJAIPUR-AURAIYA-PHULPUR PIPELINE PROJECT.

Reported Date : 10-MAY-21

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 6 / 2021

Cost Overrun (%)-   0

Time Overrun (Months)-    9

Total/Pending/Completed Milestone - 24 / 3 / 21

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2881.402000

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1612.84.13.71620.6

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20200/09/2021

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1250

Ministry Review Date

LatestLastPhysical Progress (%)Status
93.7Ongoing

Monthly Status

Background Information

• Construction Status: Panchnama- Completed, welding: 349.7 km, Lowering: 347.2 km. Gas in done in 174 Km section.• Construction Status: Panchnama: Completed, welding: 347.6 km, Lowering: 340.8 km. Gas in for 175 Km completed.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone