Reported Date :
07-SEP-22
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
8
/
2022
|
Cost Overrun (%)- 0
|
Time Overrun (Months)-
20
|
Total/Pending/Completed Milestone -
24
/
0
/
24
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
¿ Dobhi to Durgapur section (30” X 348.3 km) & spur to Matix fertilizers (12” X 1.7 Km): Commissioned & dedicated to the nation by Hon’ble PM on 07.02.2021.
¿ Spurline to HURL Sindri (12” X 9.2 Km): Commissioned on 02.06.2021
¿ Spurline to CGS Jamshedpur (12” X 123.2 Km): Entire pipeline mechanically completed on 30.08.2022.
| |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |