• Construction work started in Dec’21. Progress is as follows:
Mainline: Scope-264 Km, Panchnama / RoU Handover – 262 Km, Welding – 234 Km, Lowering –228 Km.
Spurline: Scope- 30 Km, Panchnama / RoU Handover – 30 Km, Welding – 29.1 Km, Lowering – 27.3 Km.
• 132 Km Durgapur kolkata pipeline section completed and commissioned in Oct’2024, balance 162 km from Kolkata -Haldia construction under progress.
| Mainline: Scope-264 Km, Panchnama / RoU Handover – 240 Km, Welding – 183 Km, Lowering –166.2 Km.
Spurline: Scope- 30 Km, Panchnama / RoU Handover – 29 .5 Km, Welding – 21.5 Km, Lowering – 21.5 Km.
|