Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : GAS AUTHORITY OF INDIA LIMITED.
Project Name : DURGAPUR-HALDIA PIPELINE PROJECT.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 24 / 4 / 20

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
17402433.152433.15

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
216718.18.72193.8

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/202012/202512/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1340

Ministry Review Date

LatestLastPhysical Progress (%)Status
90Ongoing

Monthly Status

Background Information

• Construction work started in Dec’21. Progress is as follows: Mainline: Scope-264 Km, Panchnama / RoU Handover – 262 Km, Welding – 234 Km, Lowering –228 Km. Spurline: Scope- 30 Km, Panchnama / RoU Handover – 30 Km, Welding – 29.1 Km, Lowering – 27.3 Km. • 132 Km Durgapur kolkata pipeline section completed and commissioned in Oct’2024, balance 162 km from Kolkata -Haldia construction under progress. Mainline: Scope-264 Km, Panchnama / RoU Handover – 240 Km, Welding – 183 Km, Lowering –166.2 Km. Spurline: Scope- 30 Km, Panchnama / RoU Handover – 29 .5 Km, Welding – 21.5 Km, Lowering – 21.5 Km.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

 &