Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : INDIAN OIL CORPORATION LIMITED.
Project Name : SITARGANJ LPG PROJECT.

Reported Date : 26-APR-23

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 4 / 2023

Cost Overrun (%)-   0

Time Overrun (Months)-    37

Total/Pending/Completed Milestone - 26 / 0 / 26

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
160.10160.1

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
107.55018.03125.58

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
2/20203/20233/2023

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
450

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed