Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : GAS AUTHORITY OF INDIA LIMITED.
Project Name : KOCHI-KOOTTANAD-BANGALORE-MANGALORE PIPELINE PHASE-II.

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   102.71

Time Overrun (Months)-    143

Total/Pending/Completed Milestone - 42 / 1 / 41

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
291559095909

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
3547.9188.245.13781.2

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/201211/202411/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
415374.1

Ministry Review Date

LatestLastPhysical Progress (%)Status
87.5Ongoing

Monthly Status

Background Information

Construction work in progress Krishnagiri to Salem Section (146 Km): - FOA for laying tender placed on 16.03.23 & construction started. RoU Handover: 67 Km, Welding- 32.6 Km & lowering- 18.6 Km completed.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone