Reported Date :
13-FEB-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
3
/
2025
|
Cost Overrun (%)- 102.71
|
Time Overrun (Months)-
159
|
Total/Pending/Completed Milestone -
42
/
1
/
41
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
¿Krishnagiri to Salem Section (146 Km): - FOA for laying tender placed on 16.03.23 & construction work is under progress. Permission available: 127.58 Km, Working Front for lowering:115 Km, Welding- 114.4 Km & lowering-101.7 Km completed.
¿Salem to Coimbatore Section (~ 148 Km):- Order for laying & associated works placed on 19.07.2023 & construction work is under progress. Permission available: 121.3 Km, Working Front for Lowering: 58 Km, 55.4 Km welding & 45 Km lowering completed. | |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |