Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : GAS AUTHORITY OF INDIA LIMITED.
Project Name : KOCHI-KOOTTANAD-BANGALORE-MANGALORE PIPELINE PHASE-II.

Reported Date : 16-MAY-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 6 / 2024

Cost Overrun (%)-   102.71

Time Overrun (Months)-    143

Total/Pending/Completed Milestone - 42 / 1 / 41

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
291559095909

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
3781.295.412.923889.52

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/201211/202411/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
536536

Ministry Review Date

LatestLastPhysical Progress (%)Status
89.3Ongoing

Monthly Status

Background Information

Krishnagiri to Salem Section (146 Km): FOA for laying tender placed on 16.03.23 & construction started. Permission available: 128 Km, Working Front for lowering:105.9 Km, Welding- 89.2 Km & lowering- 71.8 Km completed Salem to Coimbatore Section (~ 148 Km): Order for laying & associated works placed on 19.07.2023 & construction started. Permission available: 121.3 Km, Working Front for Lowering: 43.8 Km, 44.2 Km welding & 36.5 Km lowering completed.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone