Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : GAS AUTHORITY OF INDIA LIMITED.
Project Name : KOCHI-KOOTTANAD-BANGALORE-MANGALORE PIPELINE PHASE-II.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   102.71

Time Overrun (Months)-    159

Total/Pending/Completed Milestone - 42 / 1 / 41

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
291559095909

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
3781.2379.715.34176.2

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20122/20253/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
536394.9

Ministry Review Date

LatestLastPhysical Progress (%)Status
93.7Ongoing

Monthly Status

Background Information

¿Krishnagiri to Salem Section (146 Km): - FOA for laying tender placed on 16.03.23 & construction work is under progress. Permission available: 127.58 Km, Working Front for lowering:115 Km, Welding- 114.4 Km & lowering-101.7 Km completed. ¿Salem to Coimbatore Section (~ 148 Km):- Order for laying & associated works placed on 19.07.2023 & construction work is under progress. Permission available: 121.3 Km, Working Front for Lowering: 58 Km, 55.4 Km welding & 45 Km lowering completed.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone