Sector Name : PETROLEUM.
Agency Name : GAS AUTHORITY OF INDIA LIMITED.
Project Name : KOCHI-KOOTTANAD-BANGALORE-MANGALORE PIPELINE PHASE-II.

Reported Date : 15-APR-25

Monthly Report : 5 / 2025

  

   

Total/Pending/Completed Milestone - 42 / 1 / 41

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
291559095909

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
4176.215.7102.94294.8

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/201212/202512/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
186.50

Ministry Review Date

LatestLastPhysical Progress (%)Status
94Ongoing

Monthly Status

Background Information

Krishnagiri to Salem Section (146 Km): - FOA for laying tender placed on 16.03.23 & construction work is under progress. Scope-146 km, Working Front for lowering:132 Km, Welding- 120.5 Km & lowering-108.3 Km completed. Salem to Coimbatore Section (~ 148 Km): -Order for laying & associated works placed on 19.07.2023 & construction work is under progress. Scope: 148 Km, Working Front for Lowering: 127 Km, 67 Km welding & 47.4 Km lowering completed.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks