Reported Date :
16-MAY-24
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
6
/
2024
|
Cost Overrun (%)- 102.71
|
Time Overrun (Months)-
143
|
Total/Pending/Completed Milestone -
42
/
1
/
41
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
Krishnagiri to Salem Section (146 Km):
FOA for laying tender placed on 16.03.23 & construction started. Permission available: 128 Km, Working Front for lowering:105.9 Km, Welding- 89.2 Km & lowering- 71.8 Km completed
Salem to Coimbatore Section (~ 148 Km):
Order for laying & associated works placed on 19.07.2023 & construction started. Permission available: 121.3 Km, Working Front for Lowering: 43.8 Km, 44.2 Km welding & 36.5 Km lowering completed.
| |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |