Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : GAS AUTHORITY OF INDIA LIMITED.
Project Name : CITY GAS DISTRIBUTION (CGD) NETWORK VARANASI.

Reported Date : 10-MAY-22

Monthly Report : 4 / 2022

  

   

Total/Pending/Completed Milestone - 53 / 0 / 53

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
287.490345.15

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
215.0200215.02

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
4/20220/02/2022

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks