Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : OIL & NATURAL GAS CORPORATION LIMITED.
Project Name : NW B-173A DEVELOPMENT PLAN FOR EXPLOITATION OF MUKTA PAY.

Reported Date : 17-JUL-19

Monthly Report : 5 / 2019

  

   

Total/Pending/Completed Milestone - 5 / 0 / 5

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
474.15474.15474.15

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
331.3415.431.87348.64

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
5/20195/20195/2019

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
40.770

Ministry Review Date

LatestLastPhysical Progress (%)Status
31-MAY-19100Completed

Monthly Status

Background Information

Project completed on 03.05.2019.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks