Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : OIL & NATURAL GAS CORPORATION LIMITED.
Project Name : DEVELOPMENT OF BSE-11 BLOCK.

Reported Date : 06-MAR-20

Monthly Report : 1 / 2020

  

   

Total/Pending/Completed Milestone - 5 / 0 / 5

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
511.30511.3

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
283.88262.880546.76

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
11/20190/011/2019

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
244.430

Ministry Review Date

LatestLastPhysical Progress (%)Status
31-JAN-20100Completed

Monthly Status

Background Information

Project completed on 13.10.2019.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks