Sector Name : PETROLEUM.
Agency Name : OIL & NATURAL GAS CORPORATION LIMITED.
Project Name : 4TH PHASE DEVELOPMENT OF NBP FIELD.

Reported Date : 06-MAR-20

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 1 / 2020

Cost Overrun (%)-   6.75

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 5 / 0 / 5

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
968.6101033.95

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
815.29152.820968.11

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
11/20190/011/2019

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
205.850

Ministry Review Date

LatestLastPhysical Progress (%)Status
31-JAN-20100Completed

Monthly Status

Background Information

PROJECT COMPLETED.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone