Sector Name : PETROLEUM.
Agency Name : INDIAN OIL CORPORATION LIMITED.
Project Name : CONSTRUCTION OF GRASS ROOT POL TOP AT ASANUR, TAMIL NADU.

Reported Date : 10-MAY-22

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 4 / 2022

Cost Overrun (%)-   0

Time Overrun (Months)-    17

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
466.430466.43

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
318.9304.56323.49

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
10/20203/20223/2022

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
250

Ministry Review Date

LatestLastPhysical Progress (%)Status
99Completed

Monthly Status

Background Information

Project is mechanically completed on 31st March 2022

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks