Sector Name : PETROLEUM.
Agency Name : HINDUSTAN PETROLEUM CORPORATION LIMITED.
Project Name : CONSTRUCTION OF A NEW POL DEPOT AT VILLAGE DATA IN HISAR DISTRICT IN HARYANA.

Reported Date : 06-SEP-21

Monthly Report : 8 / 2021

  

   

Total/Pending/Completed Milestone - 46 / 0 / 46

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2550300

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
269.186.50275.68

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
11/20200/00/0

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks