Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : HINDUSTAN PETROLEUM CORPORATION LIMITED.
Project Name : 180 TMTPA NEW LPG PLANT AT PATALGANGA(DIST RAIGAD), MAHARASHTRA.

Reported Date : 01-FEB-23

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 1 / 2023

Cost Overrun (%)-   11.73

Time Overrun (Months)-    27

Total/Pending/Completed Milestone - 12 / 0 / 12

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
249.26278.5278.5

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
236.741.790278.49

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20209/20229/2022

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
12.5612.56

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone