Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : INDIAN OIL CORPORATION LIMITED.
Project Name : LPG BP PROJECT MOTIHARI.

Reported Date : 11-MAY-22

Monthly Report : 4 / 2022

  

   

Total/Pending/Completed Milestone - 26 / 0 / 26

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
206.50206.5

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
179.0401.53180.57

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20213/20222/2022

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
50

Ministry Review Date

LatestLastPhysical Progress (%)Status
99.53Completed

Monthly Status

Background Information

Project has been Mechanically completed in Feb 2022. OISD and PESO clearance received in Mar 22. Project is ready for Commissioning from 31.03.2022.