Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : INDIAN OIL CORPORATION LIMITED.
Project Name : BS-VI PROJECT AT PANIPAT REFINERY.

Reported Date : 22-JUN-20

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 4 / 2020

Cost Overrun (%)-   0

Time Overrun (Months)-    N.A.

Total/Pending/Completed Milestone - 9 / 0 / 9

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
352903529

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2095.75002095.75

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
7/20190/00/0

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone