Sector Name : PETROLEUM.
Agency Name : GAS AUTHORITY OF INDIA LIMITED.
Project Name : CITY GAS DISTRIBUTION (CGD) NETWORK, RANCHI.

Reported Date : 29-APR-24

Monthly Report : 4 / 2024

  

   

Total/Pending/Completed Milestone - 19 / 0 / 19

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
226.450226.45

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
210.83046.56257.39

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
10/20220/03/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
480

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed