Reported Date :
22-JUN-20
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
4
/
2020
|
Cost Overrun (%)- 0
|
Time Overrun (Months)-
0
|
Total/Pending/Completed Milestone -
9
/
1
/
8
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
COVID19 Impact: Work was stopped at sites w.e.f 22.03.2020 due to Lockdown. However, work has now started after permission from District authorities.
¿ Steel pipeline laying under progress (Cumulative Completed) : Welding 16.58 Km
: Lowering 16.56 Km
¿ Infra for Domestic PNG Connection – (Cumulative completed) : 5875 (With Riser- Infra)
: 219 (With Meter)
¿ 2 Nos. of CNG stations commissioned.
¿ Additional 2 Nos CNG stations mechanically completed.
¿ Work in progress at 1 CNG Mother Station. | |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |