Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : GAS AUTHORITY OF INDIA LIMITED.
Project Name : CITY GAS DISTRIBUTION (CGD) NETWORK, JAMSHEDPUR.

Reported Date : 22-JUN-20

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 4 / 2020

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 9 / 1 / 8

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
221.450221.45

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
62.610.5463.59

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
10/20220/010/2022

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
2929.24

Ministry Review Date

LatestLastPhysical Progress (%)Status
39.62Completed

Monthly Status

Background Information

COVID19 Impact: Work was stopped at sites w.e.f 22.03.2020 due to Lockdown. However, work has now started after permission from District authorities. ¿ Steel pipeline laying under progress (Cumulative Completed) : Welding 16.58 Km : Lowering 16.56 Km ¿ Infra for Domestic PNG Connection – (Cumulative completed) : 5875 (With Riser- Infra) : 219 (With Meter) ¿ 2 Nos. of CNG stations commissioned. ¿ Additional 2 Nos CNG stations mechanically completed. ¿ Work in progress at 1 CNG Mother Station.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone

   </