Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : GAS AUTHORITY OF INDIA LIMITED.
Project Name : BARAUNI-GUWAHATI PIPELINE.

Reported Date : 09-OCT-23

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 9 / 2023

Cost Overrun (%)-   20.68

Time Overrun (Months)-    21

Total/Pending/Completed Milestone - 20 / 0 / 20

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
330839923992

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
3266.8278.1142.23687.1

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/202110/20239/2023

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
2700

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

- Barauni to Guwahati Pipeline (24 “X 717 Km) has been successfully completed. Gas-in done upto IP-3 (363 Km). Balance section has been commissioned with Nitrogen & is ready for Gas-in.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone