Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : OIL & NATURAL GAS CORPORATION LIMITED.
Project Name : PIPELINE REPLACEMENT PROJECT-V (OFFSHORE).

Reported Date : 25-AUG-20

Monthly Report : 7 / 2020

  

   

Total/Pending/Completed Milestone - 5 / 0 / 5

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
766.370766.37

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
539.43067.06606.49

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20190/04/2020

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
31-JUL-20100Completed

Monthly Status

Background Information

PROJECT COMPLETED ON 18.04.2020, SO PLEASE REMOVE FROM THE REPORTING LIST.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks