Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : INDIAN OIL CORPORATION LIMITED.
Project Name : ETHYLENE GLYCOL PROJECT AT PARADIP.

Reported Date : 14-FEB-23

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 2 / 2023

Cost Overrun (%)-   0

Time Overrun (Months)-    15

Total/Pending/Completed Milestone - 10 / 0 / 10

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
565405654

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
3730.54911.4504641.99

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
10/202112/20221/2023

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
691.330

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone