Reported Date :
09-MAY-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
4
/
2025
|
Cost Overrun (%)- 0
|
Time Overrun (Months)-
35
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
| Phase-I&II works completed. Phase-III to commence after commercial loading from Atchutapuram TOP. Civil-100% Mechanical-100% Electrical-87.50%,Automation-92.50%, Mechanical-II-40% & Ciivil-II-20% |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |