Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : INDIAN OIL CORPORATION LIMITED.
Project Name : PARADIP SOMNATHPUR HALDIA PIPELINE.

Reported Date : 17-OCT-23

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 10 / 2023

Cost Overrun (%)-   0

Time Overrun (Months)-    22

Total/Pending/Completed Milestone - 1 / 0 / 1

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1297.501297.5

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1110.4918.6901129.18

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
10/20214/20238/2023

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
19.70

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone