Reported Date :
11-MAR-24
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
2
/
2024
|
Cost Overrun (%)- 0
|
Time Overrun (Months)-
27
|
Total/Pending/Completed Milestone -
6
/
0
/
6
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
2G Ethanol Plant at Panipat was commissioned on 28th Apr 2023. However, the commissioning certificate formally issued in February 2024, after stabilization of unit. Unit stabilization took slightly longer time as it is a new technology and first of its kind plant constructed in India. | |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |