| Facilities:
• NOA for facility package placed to M/s LTHE Mumbai on 06.01.2021.
• Purchase Orders has been placed for all 27 critical long lead items.
Yard Activities:
TGBM (Turbine Generator Building Module): Level-1, 2, 3 & 4 structural framing completed,
painted and stacked. All equipment placed at respective deck locations. TG Model, Hot Oil expansion, Crane pedestal & boom load out completed. Module sailed out on 26.01.2023 and installed on 05.02.2023. NQL MSF (Main Structural Frame): Cellar deck, Main deck and Upper Deck stacking completed. All equipments placed at
deck locations. Load out completed. Sailed out on 25.01.2023. LQBM (Living Quarter Building module): Level-1, 2, 3, 4 & 5 structural framing completed, painted and stacked. Helideck Assembly installed on roof of LQBM. Crane installed and tested. All equipment placed. Staking of all 5 deck levels completed. Loaded out completed on 23.01.2023 and installed on 06.02.2023.
NQL Jacket: Piling and grouting of all piles
completed. Jacket installed on 28.01.2023.
NQB Jacket: Jacket installation completed on 05.01.2023. Yard activities majorly completed. DCS, ESD and F&G panel function check is in progress.
Offshore Works:
Offshore works in Season-I at Brown Field palttforms commenced from 02.01.2022. Survey related to Switchgear modification completed. Fabrication and replacement of Open and Closed Drain line and Vent Line at NQD and NQO completed. Bridge Landing Structure at NQO for NQL Completed. Cellar Deck of NQL fabricated and painted. Sub cellar deck fabrication completed. DCP skid installation completed at NQP. Structural fabrication completed at NQO platform. EDG- Engine Crank check and run test completed with hydraulic and pneumatic starting system. EDG commissioned. Installation of Bridge landing structure at NQO for new NQL-NQO bridge
completed. Instrument tube tray support installation is in progress at NQG platform. Primary fuel gas conditioning (PFGS) Skid- Testing of Loop checks, Logic checks and cause and effect with DCS system completed. Shutdown activity for HV separator completed and handed over. LP Flare line and Dry network of NQO/NQP/NQG in progress. Replacement of open and closed drain lines of NQP and NQG in progress. NQ
Complex Platform shutdown started on 15.02.2023 and completed on 24.02.2023. Sump caission scaffolding and rigging arrangement in progress at NQO. Piping activities of open drain, close drain and fire water line in progress at NQG. MCC-2, existing cable re arrangement is in progress.
Green field: Out of 81 packages, 2 packages remaining.
Brown field: NQD scope completed. NQO-NQP-NQG scope partially completed. Replacement of instruments under change order is balance.
Drilling of wells:
• Drilling of all 43 wells completed 18.12.2022.
• Production commenced from Feb’18. |