Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : OIL & NATURAL GAS CORPORATION LIMITED.
Project Name : MUMBAI HIGH SOUTH REDEVELOPMENT PHASE-IV.

Reported Date : 11-JUL-22

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 6 / 2022

Cost Overrun (%)-   2.17

Time Overrun (Months)-    12

Total/Pending/Completed Milestone - 6 / 0 / 6

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
3660.713740.053740.05

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
3453.29184.4403637.73

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
5/20215/20225/2022

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
174.420

Ministry Review Date

LatestLastPhysical Progress (%)Status
30-JUN-22100Completed

Monthly Status

Background Information

Facilities: • NOA for facility package placed to M/s LTHE Mumbai on 26.06.2019. • NWIS-R Platform installed on 07.05.2021. • One Indian flag vessel (LTB-300) deployed on 31.10.2021 for balance work. • GTG (Gas Turbine Generator) power generator unit commissioned. • All 05 Main Injection Pumps (MIP) commissioned by 29.03.2022. • Facility package of the project has been completed on 23.04.2022. Drilling of wells: • Drilling of 01 well completed during the month. • Drilling of all 30 wells completed by 08.05.2022. • Production commenced from March’19. • Project completed on 08.05.2022.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone