Reported Date :
11-JUL-22
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
6
/
2022
|
Cost Overrun (%)- 2.17
|
Time Overrun (Months)-
12
|
Total/Pending/Completed Milestone -
6
/
0
/
6
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
Facilities:
• NOA for facility package placed to M/s LTHE Mumbai on 26.06.2019.
• NWIS-R Platform installed on 07.05.2021.
• One Indian flag vessel (LTB-300) deployed on 31.10.2021 for balance work.
• GTG (Gas Turbine Generator) power generator unit commissioned.
• All 05 Main Injection Pumps (MIP) commissioned by 29.03.2022.
• Facility package of the project has been completed on 23.04.2022.
Drilling of wells:
• Drilling of 01 well completed during the month.
• Drilling of all 30 wells completed by 08.05.2022.
• Production commenced from March’19.
• Project completed on 08.05.2022. | |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |