Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : INDIAN OIL CORPORATION LIMITED.
Project Name : ADDITIONAL STORAGE TANKS AT PARADIP.

Reported Date : 05-JUN-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   19.5

Time Overrun (Months)-    42

Total/Pending/Completed Milestone - 5 / 0 / 5

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
462.3552.44552.44

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
493.7200493.72

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/202112/20243/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
63.670

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

LSTK Group A (M/s Artson): DHDT & NHT tank has been completed. VGO tank fabrication (1974/1979 completed) and welding (9833/10541 M) work under progress. LSTK Group B (M/s B&R): Tank erection and hydrotest work completed for 6 tanks: Sulphur tanks (TK-54, 55), LS-ATF tank, MS tank (TK-40), and Alkylate tanks (TK-43 and 44). Hydrotest is in progress for MS tank (TK-39). Composite Work (M/s Sopan): Work is under progress for RCC, AG pipe erection work (471,852/ 515,348 IM), UG pipe erection work (43572/48000 IM), Structural steel erection (790/835 MT), and painting.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone