Construction (Sch/Act): 100/ 98.41%
HGU Unit: Hydrogen Generation Unit has been mechanically completed on 25.01.2025.
Offsite & Utilities: U/G Piping fabrication and erection work has been completed. Remaining A/G piping fabrication, and A/G piping erection work are under progress. | Manufacturing & Delivery: All 252 nos. equipment received & 228 nos. have been erected.
Construction:-
HGU Unit:-
Equipment erection (102/113 completed), Pipe welding (93,193/106,983 ID), Structural work (BOMS: 1085/1230 MT, and Srishti: 714/879 MT completed), and electrical & instrumentation work are under progress.
Offsite & Utilities:-
HCDS compressor, Instrument air and HGU tanks work completed.
SKO tank, Cooling Tower and fire water network augmentation work is under progress.
Building works of MSS, SRR and GIS Extension is under progress.
|