Construction: Sch/Act (100/92.31):-
Standby SRU unit Mechanically completed on 25.01.2025.
Exception works including Fireproofing, piping painting, Final box up of piping systems, and instrument loop checking works are under progress. | Piling and Structural Fabrication completed, RCC work (4042/4088), Structural steel erection work (1714/1811 MT completed), UG pipe erection work (14,294/15,801 IM completed) and AG pipe erection work (123,051/139,056 IM) are in progress.
Total 37 number of equipment have been erected.
|