Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : INDIAN OIL CORPORATION LIMITED.
Project Name : INSTALLATION OF STANDBY SRU TRAIN OF 525 TPD ALONGWITH INCINERATOR AT PARADIP REFINERY.

Reported Date : 10-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 1 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    28

Total/Pending/Completed Milestone - 8 / 0 / 8

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
427.1427.1427.1

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
266.4145.720312.13

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/202212/20241/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
65.40

Ministry Review Date

LatestLastPhysical Progress (%)Status
95.9Completed

Monthly Status

Background Information

Construction: Sch/Act (100/92.31):- Standby SRU unit Mechanically completed on 25.01.2025. Exception works including Fireproofing, piping painting, Final box up of piping systems, and instrument loop checking works are under progress. Piling and Structural Fabrication completed, RCC work (4042/4088), Structural steel erection work (1714/1811 MT completed), UG pipe erection work (14,294/15,801 IM completed) and AG pipe erection work (123,051/139,056 IM) are in progress. Total 37 number of equipment have been erected.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone