Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : HINDUSTAN PETROLEUM CORPORATION LIMITED.
Project Name : CONSTRUCTION OF 80000MT LPG CAVERN AT MANGALORE.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    32

Total/Pending/Completed Milestone - 19 / 4 / 15

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
854854854

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
681.0511.663.64696.35

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20228/20258/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
4040

Ministry Review Date

LatestLastPhysical Progress (%)Status
99.5Ongoing

Monthly Status

Background Information

Cavern: • Access tunnel - Excavation completed. • Upper water curtain Tunnel - Excavation completed. • Lower Water Curtain Tunnel - Excavation completed. • Upper Connection of (S1) and (S2) - Excavation completed. • Intermediate Connection of (S1) and (S2) - Excavation completed. • Lower Connection of (S1) and (S2) - Excavation completed. • Cavern galleries (S1) and (S2) - Excavation completed. • Cavern RCC flooring completed. • Cavern cleaning 100% completed. • LWCG cleaning 100% completed. • RTD sensors fixing completed at cavern galleries. • Pressure cell installation completed. • Access tunnel plug casting completed. Non-Plant buildings and Site development: completed. AG Works • Erection of Knock out drum, Instrument Air receiver, Plant Air receiver, Cold vent stack, Seepage Water Stripper on civil foundations completed. • DG Set, Air Compressors erection done. • 6.6 KV Panel erection done. • Power Distribution Transformers erection completed. • Yard Piping completed. • Installation of HT panels, AMF completed. • Installation of DCS panels completed. • 3000 KL Treated Water Tank, 1500 KL Emergency Water Tank completed. • Power cabling works inside substation interconnecting panels completed. Field side cabling work in progress. • Civil works in SWTP area completed. • • Seepage Water Treatment Plant (SWTP) commissioning is in progress. • Fill line, Measurement line instruments, Vent Line installed. • Level Alarm line testing commissioning is in progress. • Halliburton Valve power pack installation completed. Commissioning will be after Cavern depressurisation. • Underground Hydraulic ESDVs - Hydraulic tubing in progress. • Erection of Hydrant Main Ring Header completed and Sprinkler line erection is in progress. • Gas monitoring System Installation completed. Cavern: Access tunnel - Excavation completed. Upper water curtain Tunnel - Excavation completed. Lower Water Curtain Tunnel - Excavation completed. Upper Connection of (S1) and (S2) - Excavation completed. Intermediate Connection of (S1) and (S2) - Excavation completed. Cavern leg (S1) and (S2) heading - Excavation completed. Cavern leg (S1) bench 1 - Excavation in progress. Ch. 17 / 220 mtr. completed. Cavern leg (S2) bench 2 - Excavation completed. AT3 (part of LPG storage) - Excavation completed. Operation shaft excavation completed upto 140/ 157 mtr. completed. Non-Plant buildings and Site development: completed. AG Works • Erection of Knock out drum, Instrument Air receiver, Plant Air receiver, Cold vent stack, Seepage Water Stripper on civil foundations completed. • DG Set, Air Compressors erection done. • 6.6 KV Panel erection done. • Power Distribution Transformers erection completed. • Yard Piping completed. • Installation of HT panels, AMF completed. • Installation of DCS panels completed. • 3000 KL Treated Water Tank, 1500 KL Emergency Water Tank completed. • Power cabling works inside substation interconnecting panels completed. Field side cabling work in progress. • Civil works in SWTP area completed. • Erection of SWTP package vessels - backwash tank, H2O2 tanks completed. • Piping: Fabrication Erection works are in progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone