Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : BHARAT PETROLEUM CORPORATION LIMITED.
Project Name : RESITEMENT OF RANCHI AND DHANBAD OLD POL DEPOT AT BOKARO..

Reported Date : 03-OCT-23

Monthly Report : 9 / 2023

  

   

Total/Pending/Completed Milestone - 16 / 9 / 7

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
248.550248.55

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
217.6912.122.24232.05

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20223/20235/2023

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
400

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Project is commissioned on 17th August 2023.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks