Reported Date :
29-APR-24
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
4
/
2024
|
Cost Overrun (%)- 0
|
Time Overrun (Months)-
19
|
Total/Pending/Completed Milestone -
28
/
19
/
9
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
| 1) Mechanical Erection works completed for both 2G and 1G Projects.
2) Electrical and Automation loop checking works in progress.
3) Pre Commissioning works for Individual pacakge to commence. |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |