Block A, B, C & D Blockworks at all floors, facade, finishing and MEP jobs and electrical conduit in progress.
Block E: Blockworks, finishing works and electrical conduit works in progress.
Block F: Last Minor finishing works, and Facade works in progress.
Block G: Blockworks, MEP works in progress.
External firefighting works, rainwater harvesting in progress. | Block A: Blockworks at all floors, façade, finishing and MEP jobs and electrical conduit in progress.
Block B: 4th floor slab RCC for upper part and Blockwork for lower part in progress. Electrical conduit in progress.
Block C: Blockworks at all floors, façade, finishing and MEP jobs and electrical conduit in progress.
Block D: Blockworks at all floors, façade, finishing and MEP jobs and electrical conduit in progress.
Block E: Blockworks, finishing works and electrical conduit works in progress.
Block F: façade works in progress.
Block G: Blockworks, MEP works in progress.
Retaining wall / abutment work completed and scoop pile foundation works completed.
Super-structure under fabrication. External firefighting works started at site. |