Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : INDIAN OIL CORPORATION LIMITED.
Project Name : PX-PTA REVAMP AT PANIPAT REFINERY.

Reported Date : 12-JAN-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 1 / 2024

Cost Overrun (%)-   0

Time Overrun (Months)-    24

Total/Pending/Completed Milestone - 7 / 0 / 7

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
125501255

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
750.78155.340906.12

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/202112/202312/2023

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
112.470

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone