Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : NUMALIGARH REFINERY LIMITED.
Project Name : NUMALIGARH REFINERY EXPANSION PROJECT 6 MMTPA REFINARY.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 14 / 6 / 8

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
12366018968

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
15390.8262334416357.82

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
10/20240/012/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
43020

Ministry Review Date

LatestLastPhysical Progress (%)Status
74.92Ongoing