Sector Name : PETROLEUM.
Agency Name : INDIAN OIL CORPORATION LIMITED.
Project Name : COMPRESSED BIO GAS PLANT AT GORAKHPUR.

Reported Date : 05-APR-24

Monthly Report : 3 / 2024

  

   

Total/Pending/Completed Milestone - 9 / 0 / 9

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
164.690164.69

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
115.2230.07.34145.63

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
7/20213/20223/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
120

Ministry Review Date

LatestLastPhysical Progress (%)Status
99Completed

Monthly Status

Background Information

Mechanically completed in Jan-2024. Partial raw Bio gas generated. Commissioning in progress.