Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : HINDUSTAN PETROLEUM CORPORATION LIMITED.
Project Name : BARMER PALANPUR PIPELINE.

Reported Date : 30-DEC-22

Monthly Report : 12 / 2022

  

   

Total/Pending/Completed Milestone - 20 / 0 / 20

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
7760764

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
497.06101.11165.83764

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
11/202211/202211/2022

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
172140

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks