Reported Date :
07-MAY-24
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
4
/
2024
|
Cost Overrun (%)- 0
|
Time Overrun (Months)-
0
|
Total/Pending/Completed Milestone -
52
/
2
/
50
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
Jind to Narwana-Forest permission pending for laying steel pipeline. Patiala Chowk to HSIIDC Jind-PWD permission pending. Jind Rohtak road NH352-Permission pending. Jind bypass to Amandeep plant-File forwarded to RO for approval. MDPE pipeline laying of 8 kms in the current month and FY2024-25 is 8 Kms. Cumulatively 528 KM of MDPE pipeline has been laid so far. Steel Pipeline laying of 4 Inch-Kms in the current month and FY2024-25 is 4 Inch-KM. Cumulatively 1154 inch-KM of steel pipeline has been laid so far. LNG connections-current year-257, Cumulative LMC-8165 | MDPE pipeline laying of 11 kms in the current month.
Steel Pipeline laying of 1 Inch-Km in the current month.
3 CNG stations commissioned during the month.
|
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |