Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : INDIAN OIL CORPORATION LIMITED.
Project Name : BARAUNI REFINERY CAPACITY EXPANSION FROM 6.0 TO 9.0 MMTPA.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   22.3

Time Overrun (Months)-    40

Total/Pending/Completed Milestone - 7 / 1 / 6

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
148101811318113

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
10482.63185.65230.3510898.63

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
4/20238/20268/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
2098.010

Ministry Review Date

LatestLastPhysical Progress (%)Status
85.7Ongoing

Monthly Status

Background Information

AVU: Equipment erection, Piping erection, Structural erection, Cable laying & insulation work are in progress. OHCU: Structural erection, Piping fabrication & erection, equipment erection & electrical & equipment erection jobs in progress. DHDT: Structural erection and piping fabrication & erection jobs in progress. SRU: RCC and Structural fabrication and erection & piping fabrication & erection in progress. NHT ISOM: Structural fabrication & erection and piping fabrication in progress. Piping erection started PPU: RCC, Structural erection and Piping fabrication & erection and electrical cable laying in progress. PRU: RCC work and Structural fabrication & erection, piping fabrication & erection in progress. RFCC Revamp: Structural and piping fabrication and erection works in progress. Coker-B Revamp: Structural steel and piping fabrication & erection in progress. Hydrogen and Nitrogen: Structural fabrication & erection, Piping Fabrication & erection work in progress.AVU: 328 out of 329 eqpt equipment dispatched and received at site. Equipment erection, Piping fabrication & erection, Structural erection, Electrical cable laying works are in progress. OHCU: 236 out of 243 eqpmnt dispatched and 234 received at site. RCC, Structural erection, Piping fabrication & erection jobs in progress. DHDT: RCC, Structural fabrication & erection and piping fabrication jobs in progress. SRU: RCC and Structural fabrication and erection in progress. NHT ISOM: RCC, Structural fabrication & erection and piping fabrication in progress. PPU: RCC, Structural fabrication & erection and Piping fabrication in progress. PRU: Piling, RCC work and Structural fabrication in progress. RFCC Revamp: Civil & Structural and piping fabrication and erection works in progress. Coker B Revamp: Structural steel dismantling, Piping (Reroute) fabrication and erection in progress. Hydrogen and Nitrogen: RCC works, Structural fabrication & UG Piping Fabrication work in progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone