Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : HINDUSTAN PETROLEUM CORPORATION LIMITED.
Project Name : CITY GAS DISTRIBUTION IN UP AND UK.

Reported Date : 07-MAY-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 4 / 2024

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 64 / 30 / 34

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
3450.203450.2

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1505.50456.521962.02

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20293/20293/2029

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
2200

Ministry Review Date

LatestLastPhysical Progress (%)Status
48.5Completed

Monthly Status

Background Information

Steel Pipe laying in this month-66 inch-KM, Cumulative Laying-4157 Inch-km. MDPE Laying in this month-24 KM, Cumulative–2332 KM, CNG stations cumulative-204.162 in-KM of steel and 91 KM of MDPE laid during the month. 27 CNG stations commissioned during the month.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone