Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : GAS AUTHORITY OF INDIA LIMITED.
Project Name : SRIKAKULAM ANGUL PIPELINE PROJECT.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    41

Total/Pending/Completed Milestone - 18 / 1 / 17

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2658.3402658.34

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2132.740.602173.3

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
7/20226/202512/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1570

Ministry Review Date

LatestLastPhysical Progress (%)Status
94.4Ongoing

Monthly Status

Background Information

• SAPL Mainline (~421 Km): RoU Handover- 421 Km, Welding- 421 Km, Lowering- 421 Km, Hydrotest- 421 Km. • SAPL Spurline (322 Km): RoU Handover- 289 Km, Welding- 267 Km, Lowering- 253 Km, Hydrotest-100.7 Km. • SAPL Mainline (~421 Km): RoU Handover- 420.9 Km, Welding- 420.9 Km, Lowering- 420.9 Km, Hydrotest- 323.8 Km. • SAPL Spurline (321 Km): RoU Handover- 296 Km, Welding- 227.2 Km, Lowering- 191.6 Km.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone

   <