Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : GAS AUTHORITY OF INDIA LIMITED.
Project Name : SRIKAKULAM ANGUL PIPELINE PROJECT.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 18 / 1 / 17

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2658.3402658.34

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2132.740.65.82179.1

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
7/202212/202512/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1570

Ministry Review Date

LatestLastPhysical Progress (%)Status
94.6Ongoing

Monthly Status

Background Information

• SAPL Mainline (~421 Km): RoU Handover- 421 Km, Welding- 421 Km, Lowering- 421 Km, Hydrotest- 421 Km. • SAPL Spurline (322 Km): RoU Handover- 322 Km, Welding- 271 Km, Lowering- 258 Km, Hydrotest-100.7 Km. • SAPL Mainline (~421 Km): RoU Handover- 420.9 Km, Welding- 420.9 Km, Lowering- 420.9 Km, Hydrotest- 323.8 Km. • SAPL Spurline (321 Km): RoU Handover- 296 Km, Welding- 227.2 Km, Lowering- 191.6 Km.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

   <