Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : GAS AUTHORITY OF INDIA LIMITED.
Project Name : CITY GAS DISTRIBUTION, JAMSHEDPUR.

Reported Date : 01-MAY-24

Monthly Report : 4 / 2024

  

   

Total/Pending/Completed Milestone - 9 / 0 / 9

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
221.450221.45

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
150.66086.37237.03

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
10/20220/03/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
340

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks