Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : INDIAN OIL CORPORATION LIMITED.
Project Name : INFRASTRUCTURE DEVELOPMENT FOR UTILIZATION OF NATURAL GAS AT PARADIP REFINERY.

Reported Date : 05-APR-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   0

Time Overrun (Months)-    20

Total/Pending/Completed Milestone - 4 / 0 / 4

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
202.160202.16

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
129.4219.932.74152.09

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
7/20220/03/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
9.010

Ministry Review Date

LatestLastPhysical Progress (%)Status
90.4Completed

Monthly Status

Background Information

Mechanically Completed.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone