Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : INDIAN OIL CORPORATION LIMITED.
Project Name : INTEGRATED PARA XYLENE (PX) AND PURIFIED TEREPHTHALIC ACID (PTA) PROJECT AT PARADIP REFINERY.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    27

Total/Pending/Completed Milestone - 12 / 4 / 8

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
13805013805

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
7155.5918357.897531.48

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
1/20244/20254/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1524.070

Ministry Review Date

LatestLastPhysical Progress (%)Status
89.7Ongoing

Monthly Status

Background Information

Manufacturing- PTA-319/323 equipment received PX-389/412 equipment received ETP-389/409 equipment received O&U- 38/67 equipment recieved CONSTRUCTION:- PTA Concreting Work (76,568 / 82,520 Cum), Structural Erection (7,051 / 7,448 MT), Piping Erection (654,764 / 836,499 ID), Equipment Erection (288 / 323) in progress. PX Concreting Work (84,971 / 118,093 Cum) Structural Erection (15,214 / 15,580 MT), Piping Erection (1,065,783 / 1,593,905 ID), Equipment Erection (383 / 412) in progress. ETP Concreting Work (17,415 / 20,391 Cum), Structural Fabrication (799 / 829 MT), Structural Erection (371 / 859 MT), Equipment Erection (116 / 389) in progress. O&U Concreting Work (67,681 / 91,019 Cum), Structural Fabrication (12,283 / 12,379 MT), Structural Erection (8,444 / 12,379 MT), Pipe Erection (309,420 / 849,661 ID), Equipment Erection (13 / 38) in progress.Manufacturing- PTA-254/323 equipment received PX-386/412 equipment received ETP-250/409 equipment received O&U- 6/67 equipment recieved CONSTRUCTION:- PTA:- Piling completed, concreting work (58,179/82,221 completed), Str Fabrication (7378/7448), Str erection (5213/7448), and piping erection work (259,879/843,289 ID completed) are in progress. PX:- Piling and Structural fabrication completed, concreting work (69,890/113,658 Cum completed), Str Erection (11,743/15,580 completed), and pipe erection (419,110/ 1,399,189 ID completed) are under progress. ETP:-Piling completed (1514), concreting work (11,633/19,016 completed), Structural fabrication (101/560 MT), and pipe fabrication work (1756/100,000 ID) are under progress. O&U:- Piling (7379/7504 completed), concreting work (42,994/71,548 completed), Str Fabrication (6,898/12,059 completed), Str Erection (3371/12,059 completed), and pipe fabrication (21,547/145,526 ID completed) are under progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone