Manufacturing-
PTA-321/323 equipment received
PX-412/412 equipment received
ETP-389/408 equipment received
O&U- 38/67 equipment recieved
CONSTRUCTION
PTA Concreting Work: 76,568 / 82,520 Cum Structural Erection: 7,134 / 7,448 MT Piping Erection: 680,301 / 836,499 ID Equipment Erection: 292 / 323 Insulation in progress on multiple equipment
PX Concreting Work: 84,971 / 118,093 Cum Structural Erection: 15,287 / 15,580 MT Piping Erection: 1,065,783 / 1,593,905 ID Equipment Erection: 384 / 412 Hydrotesting: 10 / 14 tanks Completed
ETP Concreting Work: 17,415 / 20,391 Cum Structural Fabrication: 836 / 852 MT Structural Erection: 385 / 852 MT Equipment Erection: 123 / 408 Equalization Tank-II: Hydrotesting underway ASB Panel Erection: Completed
O&U Concreting Work: 67,681 / 91,019 Cum Structural Fabrication: 12,315 / 12,379 MT Structural Erection: 8,630 / 12,379 MT Pipe Erection: 309,420 / 849,661 ID Equipment Erection: 13 / 67 Chimney RCC: Superstructure RCC completed
| Manufacturing-
PTA-254/323 equipment received
PX-386/412 equipment received
ETP-250/409 equipment received
O&U- 6/67 equipment recieved
CONSTRUCTION:-
PTA:- Piling completed, concreting work (58,179/82,221 completed), Str Fabrication (7378/7448), Str erection (5213/7448), and piping erection work (259,879/843,289 ID completed) are in progress.
PX:- Piling and Structural fabrication completed, concreting work (69,890/113,658 Cum completed), Str Erection (11,743/15,580 completed), and pipe erection (419,110/ 1,399,189 ID completed) are under progress.
ETP:-Piling completed (1514), concreting work (11,633/19,016 completed), Structural fabrication (101/560 MT), and pipe fabrication work (1756/100,000 ID) are under progress.
O&U:- Piling (7379/7504 completed), concreting work (42,994/71,548 completed), Str Fabrication (6,898/12,059 completed), Str Erection (3371/12,059 completed), and pipe fabrication (21,547/145,526 ID completed) are under progress.
|