Manufacturing-
PTA-319/323 equipment received
PX-389/412 equipment received
ETP-389/409 equipment received
O&U- 38/67 equipment recieved
CONSTRUCTION:-
PTA Concreting Work (76,568 / 82,520 Cum), Structural Erection (7,051 / 7,448 MT), Piping Erection (654,764 / 836,499 ID), Equipment Erection (288 / 323) in progress.
PX Concreting Work (84,971 / 118,093 Cum) Structural Erection (15,214 / 15,580 MT), Piping Erection (1,065,783 / 1,593,905 ID), Equipment Erection (383 / 412) in progress.
ETP Concreting Work (17,415 / 20,391 Cum), Structural Fabrication (799 / 829 MT), Structural Erection (371 / 859 MT), Equipment Erection (116 / 389) in progress.
O&U Concreting Work (67,681 / 91,019 Cum), Structural Fabrication (12,283 / 12,379 MT), Structural Erection (8,444 / 12,379 MT), Pipe Erection (309,420 / 849,661 ID), Equipment Erection (13 / 38) in progress. | Manufacturing-
PTA-254/323 equipment received
PX-386/412 equipment received
ETP-250/409 equipment received
O&U- 6/67 equipment recieved
CONSTRUCTION:-
PTA:- Piling completed, concreting work (58,179/82,221 completed), Str Fabrication (7378/7448), Str erection (5213/7448), and piping erection work (259,879/843,289 ID completed) are in progress.
PX:- Piling and Structural fabrication completed, concreting work (69,890/113,658 Cum completed), Str Erection (11,743/15,580 completed), and pipe erection (419,110/ 1,399,189 ID completed) are under progress.
ETP:-Piling completed (1514), concreting work (11,633/19,016 completed), Structural fabrication (101/560 MT), and pipe fabrication work (1756/100,000 ID) are under progress.
O&U:- Piling (7379/7504 completed), concreting work (42,994/71,548 completed), Str Fabrication (6,898/12,059 completed), Str Erection (3371/12,059 completed), and pipe fabrication (21,547/145,526 ID completed) are under progress.
|