Project Summary
Project Summary
Sector Name : PETROLEUM.
Agency Name : BHARAT PETROLEUM CORPORATION LIMITED.
Project Name : ENHANCING PRODUCTION OF LUBE OIL BASE STOCK (LOBS) PROJECT AT MUMBAI REFINERY.

Reported Date : 06-SEP-22

Monthly Report : 8 / 2022

  

   

Total/Pending/Completed Milestone - 11 / 2 / 9

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
6400640

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
404.5919.710424.3

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20210/07/2022

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1200

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks