Sector Name : PETROLEUM.
Agency Name : GAS AUTHORITY OF INDIA LIMITED.
Project Name : MUMBAI NAGPUR JHARSUGUDA PIPELINE PROJECT.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    28

Total/Pending/Completed Milestone - 29 / 2 / 27

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
7844.2507844.25

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
6224.341.783.96349.9

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
5/20236/20259/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
3000

Ministry Review Date

LatestLastPhysical Progress (%)Status
94.5Ongoing

Monthly Status

Background Information

• Mumbai Nagpur section (24” X 693* Km): RoU Handover- 693 Km, Welding- 690.5 Km, Lowering- 689.9 Km, Hydrotest- 655.9 Km completed. (*Scope reduced from 698 Km to 693 Km due to shifting of originating point) • Nagpur to Jabalpur (18“X 160 Km & 12” X 157 km): RoU Handover- 317 Km, Welding-311.4 Km, Lowering- 306.3 Km, Hydrotest- 214.1 Km completed. • Nagpur Jharsuguda (18" x 692 km): RoU Handover- 692 Km, Welding-681.8 Km, Lowering-667.3 Km, Hydrotest- 300.8 Km completed. • Mumbai Nagpur section (24” X 698 Km): RoU Handover- 674 Km, Welding- 644.2 Km, Lowering- 638.9 Km, Hydrotest- 489.4 Km completed. • Nagpur to Jabalpur (18“X 160 Km & 12” X 157 km): RoU Handover- 317 Km, Welding- 257.1 Km, Lowering- 225.9 Km, Hydrotest- 9.5 Km completed. • Nagpur Jharsuguda (18" x 692 km): RoU Handover-578.6 Km, Welding- 415.1 Km, Lowering- 308.7 Km.