• Mumbai Nagpur section (24” X 693* Km): RoU Handover- 693 Km, Welding- 690.5 Km, Lowering- 689.9 Km, Hydrotest- 655.9 Km completed.
(*Scope reduced from 698 Km to 693 Km due to shifting of originating point)
• Nagpur to Jabalpur (18“X 160 Km & 12” X 157 km): RoU Handover- 317 Km, Welding-311.4 Km, Lowering- 306.3 Km, Hydrotest- 214.1 Km completed.
• Nagpur Jharsuguda (18" x 692 km): RoU Handover- 692 Km, Welding-681.8 Km, Lowering-667.3 Km, Hydrotest- 300.8 Km completed.
| • Mumbai Nagpur section (24” X 698 Km): RoU Handover- 674 Km, Welding- 644.2 Km, Lowering- 638.9 Km, Hydrotest- 489.4 Km completed.
• Nagpur to Jabalpur (18“X 160 Km & 12” X 157 km): RoU Handover- 317 Km, Welding- 257.1 Km, Lowering- 225.9 Km, Hydrotest- 9.5 Km completed.
• Nagpur Jharsuguda (18" x 692 km): RoU Handover-578.6 Km, Welding- 415.1 Km, Lowering- 308.7 Km.
|